NEPA, Electrical Energy and
Nigeria
Unbundling Some Issues
By
Mobolaji E. Aluko,
PhD
alukome@comcast.net
Burtonsville,
MD, USA
December 19, 2004
INTRODUCTION
I am often amused when I read
NEPA officials as well as other political operatives of the present civilian
administration boast that while before 1999, the electric energy output of the
country was roughly 1700 MW out of a total capacity of 6000, they have been able
to maintain it steadily in the 2500 3200 MW range, and surprise, surprise !
- have even for a period attained a peak of 4, 200 MW, and that they are now
aiming for 10,000 MW by the year 2010 ! These government
officials are quick to trot out where and how electrical energy is produced in
Nigeria (See Table 1) and big plans for new ones (See Table 2).
So how big are 1,700, 3,200,
4,200, 6,000 and 10,000 MW ? Puny amounts of electric power for a country 140
million strong, if you ask me !
So what is all this boasting
about ? Quite amazing.
The question as to how much
energy (in form of electricity)
Nigeria
really needs is never emphasized. To answer this
question among several other important questions - we first need to do some
quick energy arithmetic and then look at some international benchmarks.
BACK-OF-THE-ENVELOPE ELECTRICAL ENERGY ARITHMETIC
We are all familiar with the 60
Watt bulb, but for the moment, let us look on the brighter side and consider the
100 Watt bulb, and assume that ten of those (that could light up 5 standard size
living or bedrooms or areas) are turned on 24 hours in a day and 7 days in a
week. That will require a 1,000 Watt generating power or 1
kW power-generating plant running 24/7, assuming no power losses from the
generation point through the transmission line to the delivery site of the
bulbs. 10,000 of those 100-Watt bulbs will therefore require
a 1 MW power plant. [1 MW = 1,000 kW = 1,000,000 W ]
Watts
and megawatts are units of power, which, if deployed
in time, produce energy to do electric work. The unit of
such energy is watt-hr (a watt of power deployed over one hour) or the , KWh or
the MWh as the case may be.
I MW of a power station running
24/7 (assuming 100% efficiency) produces roughly 0.01
billion kWh in one year (calculated from 1000 Kw x 24 hrs per day * 365 days per
year ). That means that a 100 MW power plant a good standard for sizing such
plants - produces about 1 billion kWh (or 1 terawatt-hour)
annually.
A COMPARISON WITH
OTHER NATIONS
From the above quick
arithmetic,
Nigeria
s maximum-capacity generating plants of 6,000 MW
should therefore be producing 60 billion kWh annually if running constantly.
Now I have been looking at
several countries around the world thirty-five countries to
be exact - to assess their electrical energy production and usage. You will find
the results in Table 3, arranged within each class of
countries in order of declining per capita electricity production.
First we find that
Nigeria
is listed as having produced in the year 2001 just
15.67 billion kWh. That would mean that even though we
sometimes attain 3000 4000 MW power peak output - that is half- to two-thirds
the maximum POWER rated the actual energy output is 15.67/60 or more like
one-quarter ! That is point number 1: that there is a
difference between power available and energy delivered, and in fact we have
SERIOUS energy KWASHIOKOR in that country of ours!
These observations however need
to be qualified, bearing in mind that these figures do not include the various
PRIVATE generators humming all over the country, all generating immeasurable
PRIVATE electricity (and noise to boot) to homes, offices and industries.
Nevertheless, the figures serve as a yardstick for measuring NEPA both
in terms of its competency and how far it still needs to go to achieve success
as a electricity service provider.
Point Number 2 has to do with
comparing our per capita production of electrical energy with that of other
nations. In closely inspecting Table 3, you will notice that
electrical energy production and usage are invariably close to each other, any
difference between them being made up almost exactly by exported or imported
quantities. This is because electrical energy, once produced
or unused, cannot be stored as such. So let us focus only
on electrical energy production total and per capita.
On a purely market size basis
(total energy production), US,
China
,
Brazil
and
South Africa
are the leaders in their respective geographical
categories, with the
US
producing almost 570 billon kWh down to
South Africa
producing about 200 billion kWh in 2001.
On a per-capita energy production basis (it is convenient to state it on
a per million people basis here), Canada, Australia, Paraguay and again South
Africa are the leaders, with Canada at 17.4 billion kWh per million people, and
South Africa at 4.6 billion kWh per million people.
Nigerias stated figures are
15.67 billion kWh total energy production and 0.11 billion kWh per million
people, which is roughly equivalent to having a constantly-running 11 MW of
power station per million people, or a total of 1,500 MW for the country.
You will also notice that if, for example,
Nigeria
were to produce electricity at the
USA
rate of 12.7 Billion kWh per million people - which
is equivalent to having a 1,270 MW plant per million people (or 1.270 MW per
thousand people) - then with a population of 137 million, we should have power
plants totaling 174,000 MW. If, on the other hand, we were to compare ourselves
with
South Africa
, we should have power plants totaling 63,000 MW,
which is ten times what we have now. [
South Africa
is predicting that it will need 20,000 MW ADDITIONAL
electrical power by 2022 ! Pretty scary
]
Similar comparisons can be made
with other nations to serve as guidelines for developing our electrical energy
production sector.
WHAT ARE THE
PROBLEMS HERE ?
NEPA officials, its watchers
and energy experts have identified several problems with NEPA itself, namely:
(1)
in generation
The fewness and sparse
distribution of generation points relative to the size of the country presents a
problem. The first problem is that clearly we have not
invested sufficiently in total generating capacity, apparently being satisfied
with present estimated demands rather than a visionary attitude that more
electricity generates demand for even more. Secondly, the
8 generation stations with more than half located along
the coast and the rest along the midsection of the country with a capacity of
6,000 MW is on average 750 MW per generating station.
When one station shuts down or has a problem due to poor water levels,
disrupted fuel supply or turbine breakdown or outright sabotage -
it takes down a whole portion of the country with it, with no possibility
of convening the help of a nearby station.
Thus, on the whole, the average
per-station power generated needs to be cut to no more than 100 MW by building
smaller power plants (both private and private/public partnership) and
distributing them more around the country.
(2)
in transmission
The sparse geographical
distribution of generation points also means that average distances over which
electrical energy is distributed are high anywhere from 300 500 kilometers.
This results in line voltage and power losses as high as 25% in Nigeria
(compared with 3% in the US and 0.5% in Japan) particularly since the grid
voltages in Nigeria are typically 330 kV compared with increasingly 765 kV in
developed countries [For a given power, the higher the grid line voltage, the
smaller the grid current, and hence for a given length of wire, the smaller the
line power loss by a power of two].
Distribution problems are
compounded when electrical wires are stolen and power transformers (for stepping
down and stepping up voltages along the way) are broken down.
Thus, reducing distribution
distances, increasing the gridline voltages, improving security and maintenance
culture are clear steps to be taken here.
(3)
in distribution and
marketing
At the end of the day, somebody
must pay for the energy generated, and that should be the consumer
residential, commercial and industrial - to whom the
electricity is distributed at the appropriate voltages (240 volts for
residential and commercial users in Nigeria, and higher for some commercial and
industrial users). As at June 2002, NEPAs revenue customer base was put at
about 3.05 million - 83% of which where residential, 16%
commercial and 0.4% industrial. In a country that is 137
million, with 446 Local government areas (or 57.6%) out of
774 are connected to the national grid, and 35% of them
having some connection to NEPA, that is a pitiful pitiful customer base.
Zero-voltage (blackouts),
sustained low voltage (brown-outs) or frequent heavily fluctuating voltages have
been the order of the day in the experience of Nigerians, making the desire to
pay for such poor quality service quite understandably low.
Poor recording of electricity use by customers, poor
collection methods and outright fraud (payments not remitted to NEPA) have been
major problems.
It would appear that the
introduction of pre-payment methods will go a long way to solving these problems
but not those of blackouts, brownouts and heavily-fluctuating voltages,
unless the increased revenue is appropriately re-directed !
UNBUNDLING NEPA 6
GENCOS, 1 TRANSCO AND 11 DISCOS
In line with the Obasanjo
regimes mantra of liberalization and privatization, and complaint about large
sums of money being spent on NEPA without measurable improvement, it
has pledged to sell off NEPA to private hands, with the latest date (after many
shifts) being sometime in 2005. As it waits for the Electric
Power Sector Reform (EPSR) Bill presently with the National Assembly
to be passed into law, it has recently unbundled NEPA into various 6
Generating Companies (Gencos) based around the present major generating plants,
1 Transmission Company and 6 Distribution Company (Discos),
with these new business units being slated to be sold off to
private hands as willing buyers come along. [See Table 4.]
One would have expected that
both the six generating and eleven distribution companies should have been
unbundled along the six geographic zones. Anyway, we live to
see how this unbundling will ensure electricity at all not to talk of constant
one - in my Ode-Ekiti village !
WHAT EACH STATE IN
NIGERIA
SHOULD DO WITH RESPECT TO (ELECTRICAL)
ENERGY
Each state or administrative
unit in our country needs to adopt a clear energy policy if it is achieve any
semblance of economic development. To fix ideas, let us
consider a brief discussion of estimating the electricity demand in my
Ekiti
State
as an example of such an energy policy.
I estimate that
Ekiti
State
currently has a population of about 2.5 million
people (1991 Census put us as 1.647 million; we were then part of
Ondo
State
). If we compare ourselves with the
US
, then we would need 3,175 MW for Ekiti state; if it
is with
South Africa
, we will need 1,150 MW. At the
present capacity of
Nigeria
, we will need 27.5 MW.
Currently, Ekiti State has ZERO power plant, and all of our electrical
energy all 5 10 MW of it - comes from far away Kainji hydro-Dam, and even
that via Akure.
To my mind, I think that
Ekiti
State
should aim for 5 - 10 times better than the average
of
Nigeria
right now, so we should go for a 150 MW - 300 MW
electric generating station.
What mix of energy sources
hydro, thermal, solar and wind - would supply such power to
Ekiti
State
? I have provided a sample in Table 5.
It may be controversial, but
personally, I have added in a consideration for NUCLEAR
REACTORS, which are not really as dangerous as they are cracked up to be in the
press ! However, traditional pressurized water (nuclear)
reactors (PWR) produce energy of the order of 1,000 MW,
which would be too big (and costly) for
Ekiti
State
for the conceivable future.
http://www.eia.doe.gov/cneaf/nuclear/page/nuc_generation/gensum.html
US Nuclear Energy generation
http://www.eia.doe.gov/cneaf/nuclear/page/nuc_generation/usreact03.xls
Nuclear Reactors in the
United States
However, one or two new
micro-nuclear reactors (some Pebble Bed Modular Reactors PMBR are being
developed in South Africa, at 110 MW each) could supply all that we need in
Ekiti State without requiring oil and gas transportation from the Niger-Delta to
Ekiti, without too much nuclear accident endangerment.
See:
www.world-nuclear.org/sym/1999/pdfs/kemm.pdf
Development of
South Africa
nuclear PBMR
I admit that micro-nuclear
reactor deployment is still some many years off, after all the proper research
is done, but we should continue to keep an eye on it and have Nigerian academics
ENGAGE in meaningful research on it in our Energy Research Centers.
Now, with regard to energy from
renewables such as solar and wind, one cannot REALISTICALLY expect to generate
more than 10% of our energy requirements, so I have
distributed them evenly (5% each) in Table 5. Being left with Hydro and Thermal
sources, since we have no large water falls (but a few dams) in
Ekiti
State
, their distributions have been
made 20%-70% Hydro-Thermal.
The upshot of all the above is
that for Ekiti State, a mix of 2 Thermal Units (to make a total of approximately
200 MW) and 1 Hydro unit (of equivalent of 100 MW; from various micro-dams) will
be what we need, staged and financed in any way that we can afford.
Similar considerations can be
made by other states.
EPILOGUE
Electrical energy is the most
mobile and versatile form of energy, and its good quality and quality are
absolutely essential for economic and technological development.
Until and unless we get its generation, transmission and
distribution/marketing right, no amount of effort in attracting foreign direct
investment into the country will yield the kind of positive results that we
want.
BIBLIOGRAPHY
http://www.ekitiketeinternationalforum.org/Aluko/Aluko%20Energy.pdf
Towards a Comprehensive Energy
Policy: From Wood to Hydrogen
[Distinguished Alumni talk to
the OAU Faculty of Technology]
Mobolaji E. Aluko
March 15, 2004
http://allafrica.com/stories/200412070741.html
Expanding NEPA's Generation
Capacity: Dream Or Reality?
This Day (
Lagos
) - ANALYSIS
December 6, 2004
Table 1:
Nigerian
Government (NEPA)* Electric Power Generating plants